GERC · Draft regulation · 19 October 2026 · Gujarat Electricity Regulatory Commission

GERC Standards of Performance (First Amendment) and Electricity Supply Code (Fifth Amendment) Regulations, 2026 — draft

Gujarat's regulator has proposed faster new connections and other consumer-service changes, aligning state rules with the Electricity (Rights of Consumers) Rules and updated CEA regulations.

Why it matters. Shorter connection timelines become enforceable service standards, with compensation exposure for discoms that miss them.

What changes

  1. New connections from the existing network within 3 days in metropolitan areas, 7 days in other urban areas and 10 days in rural areas.
  2. LT applicants up to 150 kW connected load can be connected on self-declaration, with the test report due within 45 days.
  3. Cash, cheque or demand-draft bill payment limit rises from ₹1,000 to ₹10,000; e-payment mandatory above that.
  4. Temporary connections for construction valid for up to 3 years instead of 12 months.
  5. Adds CAIFI as a reliability metric and recognises registered email for serving notices.

Who is affected

Consumers in Gujarat · Gujarat discoms · Torrent Power · Builders and developers

Official copy not yet found on the commission's website. The date shown is when the item was reported, not a confirmed issue date. Comment deadline not yet confirmed; check GERC's public notice.

Sources

Last checked 22 October 2026. Summary for information; rely on the official gazette text.