GERC Standards of Performance (First Amendment) and Electricity Supply Code (Fifth Amendment) Regulations, 2026 — draft
Gujarat's regulator has proposed faster new connections and other consumer-service changes, aligning state rules with the Electricity (Rights of Consumers) Rules and updated CEA regulations.
Why it matters. Shorter connection timelines become enforceable service standards, with compensation exposure for discoms that miss them.
What changes
- New connections from the existing network within 3 days in metropolitan areas, 7 days in other urban areas and 10 days in rural areas.
- LT applicants up to 150 kW connected load can be connected on self-declaration, with the test report due within 45 days.
- Cash, cheque or demand-draft bill payment limit rises from ₹1,000 to ₹10,000; e-payment mandatory above that.
- Temporary connections for construction valid for up to 3 years instead of 12 months.
- Adds CAIFI as a reliability metric and recognises registered email for serving notices.
Who is affected
Consumers in Gujarat · Gujarat discoms · Torrent Power · Builders and developers