CERC (Indian Electricity Grid Code) (Second Amendment) Regulations, 2026 — draft
Comments due: 2 November 2026
CERC proposes changes to the Grid Code on trial runs for storage, scheduling of infirm power, congestion charges and grid access for defaulters. Comments are now invited until 2 November 2026, with a public hearing on 4 November.
Why it matters. Sets the operating rules new storage and RE capacity must follow from first synchronisation, and puts a price on transmission congestion.
What changes
- Trial-run rules for storage: standalone ESS of 50 MW and above; storage of 250 MW or more may complete trial runs in instalments of at least 50 MW; separate provisions for pumped storage.
- Infirm power can be scheduled only after a successful trial run; if the contract is silent, it is first offered to contracted buyers with at least seven days' notice.
- Congestion charges apply when flows exceed total transfer capability; a warning is issued once flows cross available transfer capability.
- Entities in default on deviation, congestion or reactive energy charges can have their grid access restricted.
- Requests to extend the start of power interchange need documented reasons, must be filed at least 10 days ahead, with monthly updates to the RLDC; extensions are capped at three months in total.
- Most changes apply from gazette publication; amendments to paragraph 16(B) apply from 1 April 2027.
Who is affected
Generators · Storage developers · Pumped storage · RLDCs / NLDC · Transmission users · Discoms
Sources
- CERC public notice extending deadline, 22 Oct 2026 (official)OFFICIAL
- CERC draft amendment (official)OFFICIAL
- CERC public hearing notice (official)OFFICIAL