CEA Unified Framework for Digitalisation of the Distribution Sector

CEA has published a phased roadmap for discoms to move from scattered IT systems to integrated, partly automated grid operations by the mid-2030s. It is guidance, not a binding mandate.

Why it matters. Gives discoms and vendors a common sequence for spending on smart meters, SCADA and ADMS after RDSS.

What changes

  1. Foundation phase (2026–2029): readiness assessment, GIS and master data, AMI and meter data systems, feeder and transformer metering, cyber-security baselines.
  2. Integrated operations (2029–2032): link GIS, AMI, SCADA, outage management, ERP and CRM on a common network model; ADMS pilots.
  3. Intelligence and automation (2032–2035): scale up ADMS, fault location and restoration, Volt/VAR optimisation and DER management.
  4. Rule of thumb: do not automate a function until it is observable, data-quality assured and controllable; AI stays decision-support with human override at first.
  5. Proposes a national test bed for interoperability testing; smaller discoms may share non-real-time services.

Who is affected

Discoms · Smart-meter and AMI providers · IT/OT vendors · State regulators