CEA (Technical Standards for Connectivity to the Grid) Regulations, 2026 — draft
Comments due: 2 September 2026
CEA proposes new grid connectivity standards for RE, hybrid and storage connecting at 33 kV and above, including ride-through, grid-forming and black-start requirements for large batteries.
Why it matters. Moves grid-support duties onto inverter-based plants as their share of the grid grows.
What changes
- Covers renewable, hybrid and storage plants connecting at 33 kV and above; replaces the 2007 standards.
- Low- and high-voltage ride-through required for all generating units.
- Battery storage of 50 MW and above: automatic generation control, grid-forming and black-start capability, plus voltage and frequency response.
- Every unit needs a Unique Registration Number from CEA's e-GEN portal before grid connection.
- Non-compliance can lead to disconnection and action under Section 146 of the Electricity Act.
Who is affected
RE developers · BESS operators · Hybrid plants · HVDC and FACTS operators · Transmission licensees
Sources
- CEA draft (Technical Standards for Connectivity to the Grid) Regulations 2026, 31 Jul 2026 (official PDF; fetch blocked)OFFICIAL